Aldi store - Jawor

Project
Location

Jawor

Scope

Electrical installations for a store

Timeframe

Approx. 3 months

The client from Germany opened its store in Jawor on the planned day. About 3 months passed from the shell stage to the opening, and we carried out the installations to the client's guidelines, together with its inspector.

Scope of work

We were responsible for the electrical installations of the entire store: from the service connection, through the metering system and lighting, to the second fix. When needed, we also helped with the roof and air conditioning.

Opening not postponed despite a faulty switchboard. The main switchboard chosen by the client arrived with factory defects. We spotted and corrected them during the works, even though the deadline was very tight and many crews were working on site. As a result, the client did not have to postpone the store opening.

Store ready in 3 months

That is the time from the shell stage to the first day of trading.

Installations to the client's standard

We worked to the guidelines of the client from Germany, together with its inspector on site.

One company from the service connection to the checkouts

The service connection, lighting, cold rooms and POS system were handled by a single contractor. When needed, we also helped with the roof and air conditioning.

Planning a similar project?

Tell us in a few sentences what you want to do and where. We will call you back, ask about the details and prepare a free quote.

We hand over buildings on time, even when things go wrong.

D&S Investment Group is a contractor from Katowice working for companies and private clients. When the deadline is tight, we work two shifts or through the weekend so that the building is ready on the agreed day.

One company is responsible for everything

On large contracts we take on the entire job. Part of the scope, for example the roof, is done by companies we work with on a regular basis. You have one contract and do not have to work out which crew is at fault.

One company, from installations to built-in furniture

In an apartment in Będzin we did the electrical and plumbing installations, bathrooms, floors, stairs, kitchen cabinets and a sauna. You deal with one company instead of keeping an eye on several crews.

You do not have to close your building during the works

In a sports hall we replaced all the lighting while the hall stayed open the whole time. We connected a new machine at a waste incineration plant without stopping the plant.

Control your whole home from one system

In a house in Orzesze, the heating, blinds, pool, lighting and gates run on one control system. We laid the cables in about 2 weeks, alongside the finishing crew.

We do not disappear after handover

We have been looking after one client's halls for about 10 years. When a tenant changes or a hall needs to be added, they call us. Most of our new work comes from referrals from clients like these.

You can change your mind during the renovation

On the apartment in Będzin, the client changed plans many times during the work, and the whole job took about 4 months.

We work across Poland

We have already worked in Szczecin, Warsaw, Kraków, Poznań and near Wrocław, among other places.

Years of team experience
0
Halls under our ongoing maintenance
0
m² of space delivered
0 +
Let's talk

Have a deadline that cannot be moved? Write to us and we will call you back.